yen223 ◴[] No.46184611[source]
The unique thing about estimates in software engineering is that if you do it right, projects should be impossible to estimate!

Tasks that are easiest to estimate are tasks that are predictable, and repetitive. If I ask you how long it'll take to add a new database field, and you've added a new database field 100s of times in the past and each time they take 1 day, your estimate for it is going to be very spot-on.

But in the software world, predictable and repetitive tasks are also the kinds of tasks that are most easily automated, which means the time it takes to perform those tasks should asymptotically approach 0.

But if the predictable tasks take 0 time, how long a project takes will be dominated by the novel, unpredictable parts.

That's why software estimates are very hard to do.

replies(19): >>46184700 #>>46184806 #>>46184873 #>>46184947 #>>46185145 #>>46185627 #>>46185768 #>>46185915 #>>46185952 #>>46186292 #>>46186318 #>>46186774 #>>46187054 #>>46187512 #>>46188101 #>>46189271 #>>46189483 #>>46196595 #>>46201725 #
seviu ◴[] No.46184700[source]
I am in a project where we have to give estimates in hours and days.

Needless to say we always underestimate. Or overestimate. Best case we use the underestimated task as buffer for the more complex ones.

And it has been years.

Giving estimations based on complexity would at least give a clear picture.

I honestly don’t know what the PO and TL gains with this absurd obscenity.

replies(3): >>46184742 #>>46184798 #>>46185192 #
121789 ◴[] No.46184742[source]
Hours is insane. But ultimately time is money and opportunity cost. Software engineering can’t be the only engineering where you ask the engineers how much something will cost or how much time it will take and the answer is “it’s impossible to know”. Even very inaccurate estimates can be helpful for decision making if they are on the right order of magnitude
replies(4): >>46184821 #>>46184857 #>>46184975 #>>46189784 #
njovin ◴[] No.46184857{3}[source]
The next natural progression of this line of discussion between "the business" and engineering is for them to agree on a time range as an estimate. Engineering doesn't want to say it'll be done in 6 weeks, but they feel okay saying it will take between 4 and 20 weeks so this estimate is accepted.

You can guess what happens next, which is that around week 8 the business is getting pretty angry that their 4-week project is taking twice as much time as they thought, while the engineering team has encountered some really nasty surprises and is worried they'll have to push to 24 weeks.

replies(1): >>46185285 #
1. skeeter2020 ◴[] No.46185285{4}[source]
it is still better to give a range though because 1. it explicitly states the degree of unknown and 2. no boss is going to accept 4-20 weeks, which means you start talking about how you can estimate with better accuracy and the work required to do so, which is a major goal of planning & estimation.