My technique is to give an estimate with error bars. Something like 6 weeks plus or minus 2. That then leads into discussion as to what is unknown/undefined leading to the uncertainty. Sometimes the error bars are larger than the estimate because I know there will be endless feature creep and UI revisions for something like "analytics". And sometimes the number could be negative like 6 weeks plus or minus 8. That is when the functionality already exists (eg the data is already there - you can already load it into Excel and a pivot table) and could be sufficient.